Sahawatthanakit (1988) Co., Ltd.
SAHAWATTHANAKIT(1988) · Make It Smart
Back to all articles
Sahawatthanakit (1988) Engineering Team7 min read

Net-Metering in Thailand 2024 — MEA/PEA Rules, License Process, and Payback Calculation

Complete Thai Net-Metering guide — Net-Metering vs Net-Billing, MEA + PEA 2024 rules, license process steps, system size limits, payback period 4-7 years, for factories and commercial buildings

solarnet-meteringmeapeathailandlicensepayback
Net-Metering kWh meter and solar panels on Thai factory rooftop

Photo by Unsplash

สรุป (TL;DR)

Complete Thai Net-Metering guide — Net-Metering vs Net-Billing, MEA + PEA 2024 rules, license process steps, system size limits, payback period 4-7 years, for factories and commercial buildings

Why Solar Rooftop is Compelling in Thailand

Industrial electricity in Thailand averages ฿3.8-4.2/kWh (Type 4 demand charge) and commercial buildings ฿4.5-4.8/kWh — 30-50% higher than ASEAN average.

Solar panel pricing (2024-2026): ฿14-22/Wp installed — payback 4-7 years compared to:

  • Bank deposit: 1.5-2.5% IRR
  • Mutual funds: 4-7% IRR
  • Solar self-consumption: 15-25% IRR

But every project requires MEA/PEA + DOEB + ERC permits — 2024 rules changed from 1:1 Net-Metering to Net-Billing with lower export rate.


Net-Metering vs Net-Billing — Critical Distinction

graph LR
    A[Net-Metering 1:1] --> A1[Export 100 kWh = Credit 100 kWh
same rate] A --> A2[Used in early Thai pilot 2013-2018
High value, utility not profitable] B[Net-Billing] --> B1[Export 100 kWh × ฿2.2/kWh = ฿220
Import 100 kWh × ฿4.18 = ฿418] B --> B2[Used by MEA/PEA 2020+
Self-consumption preferred]

Math under Net-Billing:

  • 100 kWp installed for factory consuming ~500 kWh/day (peak hours)
  • Production ~450 kWh/day (annual ~150,000 kWh)
  • Self-consume ~380 kWh (84%) × ฿4.18 = ฿1,588/day savings
  • Export ~70 kWh (16%) × ฿2.2 = ฿154/day income
  • Total: ฿1,742/day = ฿52,260/month
  • System cost ~฿1.5-1.7M
  • Payback: 2.7-3.3 years (high self-consumption) or 4-5 years (high export)

Key insight: Self-consumption % matters most — design system to peak production matching peak load.


MEA vs PEA Coverage

Provider Coverage Best For
MEA (Metropolitan EA) Bangkok, Nonthaburi, Samut Prakan Urban factories, BKK commercial
PEA (Provincial EA) 74 other provinces Provincial factories, industrial estates

Both use same Tariff structure (Type 1-5) + similar Net-Billing rules.


License Process — Standard (200-1,000 kWp)

flowchart TD
    Start[Install Decision] --> Survey[1. Site Survey + Load Analysis]
    Survey --> Design[2. Design + Single-Line Diagram]
    Design --> Apply[3. MEA/PEA Application]
    Apply --> Review{MEA/PEA Review
30-45 days} Review -->|Approved| DOEB[4. DOEB Permit if > 200 kWp] Review -->|Reject| Revise[Revise + re-apply] DOEB --> Install[5. Install — 4-8 weeks] Install --> Test[6. Commission per IEC 61727] Test --> COD[7. Commercial Operation Date]

Required Documents (5 sets per MEA/PEA 2024)

  1. Application Form (from MEA/PEA website)
  2. Single-Line Diagram — drawn by Licensed Engineer (Phakee Wisawakorn)
  3. Technical Specifications:
    • PV module spec (Tier 1 preferred)
    • Inverter spec with IEC 61727 / IEEE 1547 test report
    • Cable + breaker spec
  4. DBD Certificate (company registration)
  5. Land Ownership Proof or rental contract ≥5 years

Timeline Reality (2024 data)

Project Size Standard Timeline
<200 kWp (Simple) 2-4 weeks
200-1,000 kWp (Standard) 1-3 months
1,000-5,000 kWp (ERC) 3-6 months
>5,000 kWp (ERC + EIA) 6-12 months

ROI Calculation Example

Scenario: Plastic factory, 5,000 m², Nonthaburi

Current bill profile:

  • Monthly consumption: 80,000 kWh
  • Average rate (Type 4): ฿4.05/kWh
  • Monthly bill: ฿324,000

Solar system design:

  • Size: 350 kWp on rooftop (capacity factor ~16% in Thailand)
  • Annual production: 490,000 kWh
  • Daily average: ~1,340 kWh

Self-consumption analysis:

  • Plant operates 7am-7pm
  • Solar peak 10am-3pm matches well
  • Estimated self-consumption: 85%

Annual savings:

  • Self-consume: 416,500 kWh × ฿4.05 = ฿1,686,825
  • Export: 73,500 kWh × ฿2.2 = ฿161,700
  • Total: ฿1,848,525/year

Investment: 350 kWp × ฿18,000/kWp = ฿6,300,000

Payback: ฿6.3M / ฿1.85M = 3.4 years

25-year cumulative net: ~฿40.7M (assuming 0.5% annual degradation, no tariff inflation)

IRR: ~22% over 25 years


Common Mistakes

1. Oversize system → low self-consumption → high export at low rate

Wrong: 500 kWp for factory peaking at 200 kW Fix: Match system size to peak daytime load × 0.85

2. Ignoring demand charge

Wrong: Only considering energy charge (฿4.05/kWh), missing demand charge (฿132-350/kW) Fix: Solar + Battery for peak shaving reduces both

3. Inverter without IEC 61727 cert

Wrong: Cheap inverter without certification Fix: Use Tier 1 brands — Sungrow, Huawei, SMA, Fronius, GoodWe

4. Skipping roof load capacity check

Wrong: Installing 12-15 kg/m² panels on weak roof Fix: Civil PE calculate roof load + sign off

5. No shading analysis

Wrong: Installing under shade of building/tree/HVAC chimney Fix: PVsyst or Helioscope simulation + drone survey


Saha Solar Service Tiers

Tier 1: Consultation (฿20-50K)

  • Site survey + drone roof image
  • 12-month load profile analysis
  • Preliminary design (3 options) + 25-yr ROI calc

Tier 2: Design + Permit (฿100-300K)

  • Single-line diagram + Licensed Engineer stamp
  • MEA/PEA + DOEB submission package
  • Project timeline

Tier 3: Turnkey EPC (฿14-18K/kWp)

  • Tier 1 procurement + installation + commissioning
  • 25-year monitoring service available

Tier 4: Long-term O&M (฿200-400/kWp/year)

  • Quarterly cleaning + inspection
  • Annual IV-curve test per IEC 61853
  • Warranty + insurance support

BOI / Tax Incentives

Incentive Benefit Eligibility
BOI Section 8 Renewable Energy 200% tax deduction >1 MWp + Thai content >40%
Section 73 Environmental 8-year tax holiday EIA-approved projects
Accelerated depreciation 100% year 1 Energy efficiency assets
EXIM Bank Green Loan 3-4% interest (vs commercial 5-6%) Verified renewable project

Summary

  • Net-Billing (not Net-Metering) is current MEA/PEA scheme 2024
  • Self-consumption % is the most important variable
  • License process: Simple (2-4 wk) → Standard (1-3 mo) → ERC (3-6 mo)
  • Realistic payback: 3.5-6 years industrial · IRR 15-25% over 25 yr
  • 5 documents required: Application + Single-line + Tech spec + DBD + Land proof
  • Common mistakes: oversize, ignore demand charge, cheap inverter, no shading analysis

Saha provides design + permit + install + commission packages — contact 02-096-2118 or visit /solar for free TCO calculator.

Share:LINEFacebook
Related Services

Need help with this in your facility?

Our team handles full procurement and installation for the topics covered in this article. Free quote within 2 hours.

Frequently Asked Questions

1

Is Net-Metering available for all meter types in Thailand?

+
No — only commercial/industrial meters (type 2.1 + 3-phase). Residential meters (type 1.x) use a separate 'Solar Roof for People' program (Net-Billing, not 1:1 Net-Metering).
2

Net-Metering vs Net-Billing — what's the difference?

+
Net-Metering = 1:1 kWh credit (export 1 unit = 1 unit credit). Not used by MEA/PEA anymore. Net-Billing = export at ~฿2.2/kWh vs import at retail ~฿4.18/kWh. Lower revenue but predictable.
3

Maximum PV system size?

+
MEA/PEA 2024 rules: <200 kWp = Simple Process, 200-1,000 kWp = Standard Process (1-3 months), >1,000 kWp = ERC License (3-6 months + EIA if >5 MWp). Self-consumption cannot exceed contracted demand (kW).
4

Realistic payback period in Thailand?

+
Industrial (Type 4, ฿3.8-4.2/kWh): 100-500 kWp = 4.5-6 years. Commercial (Type C, ฿4.5-4.8/kWh): 4-5 years. With TOU peak tariff: 3.5-5 years.
5

Is battery storage needed?

+
For grid-tie self-consumption: usually no — grid acts as 'free battery'. Battery needed only for: (1) frequent outages, (2) off-grid (remote islands), (3) TOU arbitrage. LFP battery adds ฿15-25K/kWh, extending payback 2-4 years.
Compare — buying decision

Comparison tables related to this article

Related content