Cold-Storage Food Factory — Samut Sakhon (name withheld)Private — Cold-Storage Food ManufacturerReference Pattern

3-Layer Epoxy SL + PU Topcoat Industrial Floor — 4,200 m² Cold-Storage Facility

Case study: 3-layer epoxy self-leveling + polyurethane topcoat installation for a -25°C cold-storage food factory in Samut Sakhon — BS 8204 / ISO 12944 / HACCP / GMP-compliant.

Reference Project Pattern: this is a representative engagement pattern showing what Saha can deliver to this spec. Specific client names withheld; numbers illustrative of typical project size.
2024Mueang District, Samut Sakhon

Outcomes

  • 3-layer system applied across 4,200 m²: epoxy primer + 3 mm epoxy SL + PU topcoat
  • Surface prep to ICRI CSP 3-4 — captive shot blast + diamond grinding
  • Wet coefficient of friction 0.55+ — passes TIS 2557-2554 anti-slip requirement
  • Cure time + chemical resistance verified per ASTM D2247 / ASTM D4060
  • Passed HACCP / GMP audits at 30 days and 6 months post-installation
Standards referenced
BS 8204-6:2008+A1:2010 — Synthetic resin floorings: Code of practiceISO 12944-5:2019 — Paints and varnishes — Corrosion protection of steel structuresICRI 310.2R-2013 — Selecting and Specifying Concrete Surface PreparationTIS 2557-2554 — Anti-slip floor coating (Thai industrial standard)ACI 302.2R-06 — Guide for Concrete Slabs that Receive Moisture-Sensitive Flooring
Epoxy self-leveling floor coating in a cold-storage food warehouse

Project Overview

A cold-storage food factory expanded from 2 to 5 cells, requiring 4,200 m² of new industrial floor coating that could withstand:

  • -25°C to +18°C temperature cycling (daily defrost cycle)
  • Heavy forklift traffic — counterbalance + reach trucks 3-5 tonnes, 24/7
  • Chemical exposure — sanitizer (200 ppm chlorine), brine spill, blood/protein wash
  • HACCP / GMP compliance — seamless joints with no crack/joint pathogens
  • Anti-slip safety for workforce in boots on wet floor

Sahawatthanakit (1988) delivered the full EPC scope — surface prep, coating system, cure, and a 5-year warranty.


System Design

Step 1 — Substrate Analysis

  • Concrete strength — 28-day core compression: 32 MPa (above threshold)
  • Moisture content — RH probe per ASTM F2170: 78% (above 75% threshold → moisture barrier primer required)
  • Surface pH — pH 11.2 (alkaline, acid etch needed before primer)
  • Existing coating — cure-and-seal ~0.2 mm requiring mechanical removal

Step 2 — Surface Preparation (ICRI CSP 3-4)

  • Captive shot blasting — Blastrac 1-15D with S330 steel shot
  • Diamond grinding for edges/corners unreachable by shot blaster
  • Vacuum extraction — HEPA-filtered dust collection throughout
  • Joint preparation — saw-cut V-grooves for control + expansion joints

Result: CSP 3-4 surface profile across 100% of the floor — verified with ICRI chip cards.

Step 3 — Coating System Design (3-layer)

Layer Product Application DFT
1. Primer Epoxy moisture-tolerant (≤95% RH) Roller 150-200 µm
2. Body coat Epoxy self-leveling, 100% solids Trowel + spike roller 3,000 µm (3 mm)
3. Topcoat Aliphatic polyurethane, anti-slip Roller + broadcast 200-250 µm

Total DFT: 3.4-3.5 mm — engineered for heavy forklift traffic.


Installation

Parameter Specification
Surface prep Shot blast CSP 3-4 + diamond grind + vacuum
Primer Epoxy moisture-tolerant 2-pack
Body coat 100% solids epoxy SL, 3 mm trowel-applied
Topcoat PU aliphatic + silica broadcast (anti-slip, CoF 0.55+)
Control joints V-cut + PU sealant per ACI 302
Cove base Epoxy cove 100 mm radius around wall edges (HACCP hygiene)
Cure time 24 hr inter-coat · 72 hr full cure · 7 days chemical service
Total install duration 18 working days (split-shift in vacated zones)
Warranty 5 years — coating delamination + chemical resistance

Results (8-month monitoring)

Metric Outcome
Coating area 4,200 m² (5 cold-storage cells + corridor)
Cure failures / disbond 0 at 8 months
Wet coefficient of friction 0.58 (target ≥0.50) — passes TIS 2557
Daily forklift trips absorbed 750 trips/day — no visible wear
Chemical resistance — 200 ppm chlorine Passed 24 hr immersion per ASTM D1308
HACCP / GMP audits Passed at both first audit + 6-month re-audit
Steam-wash cleaning time Reduced from 90 minutes → 45 minutes per cell

Why the Client Chose Us

  1. Cold-storage-engineered 3-layer system — moisture-tolerant primer + cold-cycle-resistant body + PU topcoat
  2. ICRI-standard surface prep — not just sweeping; measured CSP shot blasting
  3. Engineering-backed — moisture, pH, and strength tests reported pre-start
  4. HACCP/GMP compliance — cove base + sealed joints + cleanable surface
  5. 5-year warranty covering delamination + chemical attack
  6. Split-shift installation — work in zones the customer wasn't using; no operations downtime

Related Services

Looking for industrial floor coating — epoxy SL, PU topcoat, anti-slip, anti-static ESD, food-grade — for factories, warehouses, parking, OR rooms, or labs? Our team conducts free site survey + concrete testing before quoting.

Learn more: Industrial Paint Service

Comparison: Epoxy vs PU vs Acrylic Industrial Paint

TCO calculator: Paint TCO Calculator

Share:LINEFacebook
Related Services

Need help with this in your facility?

Our team handles full procurement and installation for the topics covered in this article. Free quote within 2 hours.

ตัดสินใจไหน คุ้มกว่า?

ตารางเปรียบเทียบ — สเปก + ราคา + recommendation

คำนวณแล้ว แต่ยังเลือกไม่ได้? ดูตารางเปรียบเทียบที่ละเอียดกว่า — สเปกครบ, มาตรฐาน + ตัวอย่างใช้จริง

Related content

Article

An Invoice of 107,000 Baht Pays 104,000 Into the Bank — Thai Withholding Tax Is Computed on the Pre-VAT Base

Thai withholding tax is always computed on the amount before VAT. A service invoice of 100,000 baht plus 7% VAT totals 107,000, but the 3% withholding applies to the 100,000 base — 3,000 baht — so 104,000 is what actually arrives. Why computing it on the gross total skews every invoice in the same direction, why services are withheld on but pure goods sales generally are not, and why the withheld money is not lost, only slow.

Article

How Long Should a Quotation Hold Its Price — Why 30 Days Is the Thai Standard, and Why the Expiry Date Is the Closing Tool Everyone Overlooks

The price-validity line is not a ritual at the bottom of a quotation — it is the ceiling on the cost and currency risk you carry on the customer's behalf, and the most legitimate reason to make a closing call. How to set the validity period to match the product, how to use the near-expiry window as the golden moment, and how to handle an already-expired quote without damaging the relationship.

Article

A Quote Register with Win Rate — Why Most SMEs in Thailand Cannot Tell You What Percentage of Quotes They Win

A quotation produced in Word and sent as a PDF into LINE always disappears into the chat history — no register, no status, no count of why deals were lost. How to set up a quote register that makes follow-up systematic, and how to compute win rate the way the sales-management literature actually defines it: won ÷ (won + lost), decided quotes only.

Article

Following Up on a Quote in Thailand Without Being Rude — Face-Saving Scripts and the Cadence That Works

Many Thai customers reject a price by going silent, because saying "too expensive" out loud feels like making the seller lose face — how to follow up in a way that opens the door to negotiation instead of forcing a yes/no, with a three-beat script: the first follow-up, the pre-expiry call, and the graceful close after a long silence — and why the cadence must be counted in working days, never on holidays.

Interested in a similar engagement?

Free quote within 2 hours during business hours.

Request Quote